Abu Dhabi’s Masdar and the energy company Endesa have begun building three battery storage projects at solar plants in Spain, a combined investment of €25.2 million.
The batteries will add 60.16 megawatts of capacity and 120.34 megawatt-hours of storage at plants in Extremadura and Andalusia, letting the sites hold back some of the power they generate and helping the grid absorb more renewable energy. They are the first storage projects under the partnership the two companies formed in 2024, when Masdar bought a stake in a portfolio of Endesa’s solar assets in Spain. Masdar announced the start of work in a statement published on 5 November.
The largest, Ardila, at the 44 MWp solar plants in Fregenal de la Sierra in Badajoz, will provide 36.10 MW (72.20 MWh) from 12 battery containers. La Vega I and La Vega II, at two plants in Teba in Málaga, will each provide 12.03 MW (24.07 MWh) from four containers. All three use lithium iron phosphate batteries with grid-forming inverters, which respond almost immediately to changes on the grid, and are expected to be running by the end of 2027.
Construction will create 50 jobs, and the partners have committed to using components and services of European origin.
Dr Ibraheem Almansouri, acting chief operating officer of Masdar, said: “Spain is one of Europe’s fastest-growing major economies and this growth requires secure, resilient power.”
Masdar has 4.1 GW of capacity operating across the Iberian Peninsula and about 1 GW in development, and is aiming for 100 GW worldwide by 2030.
The photo above was issued by Masdar with the announcement.